Update – week commencing 12th May 2025. Following on from our most recent updates, please find below some additional information about the works progress. Please do get in touch if you have any concerns or need further information. Deliveries of the steel sheet piles have been received. Early in the week wind speeds and sea conditions exceeded safe working conditions for pile installation. Following an improvement in conditions, piling has recommenced at the programmed rate of installation, with a total of 33 full length piles now installed safely.  You can dowload and view the FULL UPDATE HERE